

Outside/Garden
The site had been neglected for some time; the outside had got to the point of being out of control. A hedge trimmer was needed on day one to cut through the foliage and find the entrance gate. One of the main priorities has been sorting the leaking roof which needs scaffolding and space to erect this. It was decided that it was best and most cost effective to clear the entire site in one go and to fell the rotten sycamore at the main entrance too. It’s a shame to see it all go but it’s all clear now and ready for scaffolding.
Before…

After…

Before…

After…

Dartmouth Loft “Box”

Dartmouth Loft

Hello again! We’re edging ever closer to the big move now; the team has been working flat out to keep things on track. Here’s an update on what we’ve achieved over the past four weeks, why we’ve shifted to Plan B, and how everything is shaping up.
The team did an outstanding job stripping out the interior in just four days. Yes — four days! We were handed back a completely empty shell, ready for the next phase of prep.
The walls needed all the old dot-and-dab adhesive removed before painting, while the floor had to be cleared of its previous glue. The walls were relatively straightforward — one solid day of scraping, wire-brushing, and sanding had them ready for primer.
The floor, however, was another matter entirely. It needed hand-scraping to remove the tacky residue, followed by repeated rounds of sanding… day after day, evening after evening. Tough work, but absolutely worth it for the finish we’ve ended up with.
During the stripping out of the interior



All stripped out with the finished floor!

The asbestos roof had simply reached the end of its life. We could have tried patching it, but realistically it was on borrowed time — and removing it later, with a full workshop and machinery underneath, would have been almost impossible.
So, we bit the bullet. The entire asbestos roof has now been removed and replaced with a modern insulated system. The building is fully watertight and incredibly well insulated (280 mm / 11 inches), which should help keep winter heating costs under control.
The old roof

During the installation


The new roof


The roof was one of the major components of the project, and naturally the weather stepped in right on schedule to complicate matters. What was supposed to take eight days took the full eight plus an additional four-day return visit to finish the job. This has knocked the timeline back, leaving the builder with two fewer weeks than planned — hence the move to Plan B.
With the schedule tightened, the builder will now only have time to complete the reception, offices, kitchen and toilet areas before Christmas.
The workshop and loft floor will be tackled in January, which means we’re anticipating 2–3 weeks of downtime early in the new year before we’re fully up and running in the new space.
We will remain fully operational in Dartmouth until Friday 19th December. After that, we’ll begin dismantling the workshop, packing up the machines, and moving everything across to Brixham.
Our focus now turns to the final details — phone lines, post, internet, and all the other essentials that make the place function. There’ll be another update over Christmas, hopefully confirming everything is still on track and sharing the final pieces of the puzzle.